We were approached by a Body corporate in Sea Poin to Supply Power Back to the Lift and Common Areas
The Block had a Faulty Generator expensive to run and residents on the top floors were very unhappy
We Installed a 24Kw Deye Backup Sysem with 30Kw of Revov Lithium Batteries
The Power Solution will keep the lights on, and ensure lighting, access control and securtiy is maintained during Load Shedding
But most importantly provide power to the lift
The project took 3 days to install and is under constant monitoring with the Solarman App